September 2020 Update
Posted by Keller ISD Bond on 9/9/2020
The project contractor has mobilitized, installed perimter fencing around the construction zone areas of the property, set up the project job trailers, located existing utility lines, and has almost completed site grading and will start piles.
The Board of Trustees approved a GMP admendment to the construction contract with BTC in the amount of $1,196,990 for the fifth-grade addition to the building. Changes in the Vista Ridge Middle School feeder pattern necessitated the need for the additional classroom space.