Heritage Elementary Rebuild

  • Rendering of new Heritage Elementary Status: Completed
    Construction Budget: $31,146,873
    Scheduled Completion Date: July 2021
    Site Work & Existing School Demo Complete: January 2022

    Heritage Elementary School was originally built in 1987. This Bond 2019 project calls for the complete replacement of the campus on the existing campus site. Existing space on the property exists to allow for the construction of the new campus without any interruption to the existing building. After completion of the new building, the old campus will be demolished. 

    Heritage ES Project Metrics; Click for PDF

     


  • August 2021 Update

    Posted by Keller ISD Bond on 8/19/2021

    The new Florence Elementary School opened on Wednesday, August 18. 

    Keller ISD has a Temporary Certificate of Occupancy (TCO) from the City of Fort Worth. The general contractor and KISD have developed a completion plan that will be executed over the coming months as we to finish interior and exterior elements that have been delayed due to COVID-19. Site work and demolition will carry into the December/January timeframe. 

    Courtyard of new HES
    Courtyard within the new Heritage ES campus. 

    New HES Cafeteria
    New Heritage ES Cafeteria. 

     

    Comments (-1)
  • March 2021 Update

    Posted by Keller ISD Bond on 3/23/2021

    A significant amount of progress has been made on the new Heritage Elementary School, with the building still planned to open in August 2021. 

    All of the structural steel is now in place and foundation work is also complete. The building exterior is beginning to go up as is interior sheet rock. 

    courtyard of new HES
    Looking across the courtyard of the new Heritage ES campus toward classrooms. 

    View from inside the new HES gym
    Construction inside the gym at the new HES, looking toward the cafeteria. 

    main hallway of new HES
    Looking down the main hallway of the new HES from the school's future entrance.

    Looking down an administrative hallway at the new HES
    Sheet rock going up along an administrative hallway. 

     

     

    Comments (-1)
  • October 2020 Update

    Posted by Keller ISD Bond on 10/5/2020

    Aerial images show the latest progress at the Heritage Elementary construction site: 

    Aerial image of the southeast corner of the HES construction site

    Aerial image of the northeast corner of the HES construction site

    Overhead aerial of the HES construction site

    Aerial image from the northwest corner of the HES construction site

     

    Comments (-1)
  • September 2020 Update

    Posted by Keller ISD Bond on 9/9/2020

    The project contractor has mobilitized, installed perimter fencing around the construction zone areas of the property, set up the project job trailers, located existing utility lines, and has almost completed site grading and will start piles. 

    The Board of Trustees approved a GMP admendment to the construction contract with BTC in the amount of $1,196,990 for the fifth-grade addition to the building. Changes in the Vista Ridge Middle School feeder pattern necessitated the need for the additional classroom space.

    Trucks moving earth off of the new HES site  Site work taking place on the HES construction site

    Comments (-1)
  • June 2020 Update

    Posted by Keller ISD Bond on 6/17/2020

    Despite Keller ISD's COVID-19 closure, progress continues on both the Heritage Elementary and Florence Elementary projects. 

    Florence's site plan was formally approved by the Southlake City Council in April and plans for Heritage have been submitted to the City of Fort Worth. In early May, the construction manager received bids for the construction of the two projects, but with the instability of the construction market since March, the manager and VLK Architects are continuing to work to ensure that the projects both remain within budget before accepting a bid. 

    Below is a look at the preliminary design of the new Heritage Elementary School:

    Rendering of new Heritage Elementary School

    Comments (-1)
  • February 2020 Update

    Posted by Keller ISD Bond on 2/7/2020

    In January 2020, the Board of Trustees approved the design development of the new Heritage Elementary and Florence Elementary campuses from VLK Architects. View the video below to see a flyover of the preliminary designs:  

     
    Comments (-1)
  • January 2020 Update

    Posted by Keller ISD Bond on 1/24/2020

    Below is a video from the January 23, 2020, Board Meeting at which VLK's Sloan Harris describes the design process for Heritage Elementary and Florence Elementary:  

     

    Comments (-1)